Health Department Kitchen Plan Review: Nashville restaurant guide

Metro Public Health Department

What it is

Metro Health reviews your kitchen layout, equipment, finishes, sinks and plumbing before construction, under Tennessee's food service rules.

When a restaurant needs it

Whenever a food service establishment is built, extensively remodeled or converted from another use. Plans are due at least 15 days before construction starts.

How to apply

Submit the plan package to Metro Health's Kitchen Plans Review. It also appears as a Health sign-off on your Codes permit checklist (615-340-0438).

Documents you’ll need

Fee
Varies — confirm with Metro Health
Processing time
Varies
Renewal
None
Who files
Usually submitted by the architect or kitchen designer for the owner.

Good to know

Metro Health doesn't post a fixed-restaurant plan review form online. Call 615-340-0438 to confirm the current submission method and fee before you finalize drawings.

Official source

TN Dept. of Health — Plan review checklist (PDF) · Metro Codes contact list (Health kitchen plans review)

Get your personalized Nashville permit plan

Answer a few questions about your space and get every permit in order, with a timeline, a cost range, walkthroughs, and every application filled in for you to sign with Open.

Build my free plan

Last reviewed 2026-10-06. Guidance only, not legal advice.