Certificate of Occupancy (new building, change of occupancy, or Group A assembly build-out): Chicago restaurant guide

Chicago Department of Buildings

What it is

DOB's confirmation that a finished building or space may be occupied for its use. It is mandatory for new construction, a change of occupancy (for example a storefront or warehouse becoming a restaurant), and construction or substantial rehabilitation of any assembly (Group A) space regardless of size; restaurants with an occupant load of 50 or more are Group A-2.

When a restaurant needs it

New buildings; any change of occupancy to restaurant use; construction or substantial rehab of a dining space with 50+ occupants; or more than 10,000 sq ft of non-residential work. Smaller projects may request one voluntarily.

How to apply

Comes through the building permit: the permit holder schedules and passes every required inspection as work progresses, then submits the online Certificate of Occupancy Application when work is nearing completion. DOB schedules the final inspections (and gives you the Fire Prevention Bureau contact if needed), you pay any outstanding inspection fees, and you pick up the hard-copy certificate.

Documents you’ll need

Fee
No separate fee published; re-inspection fees under 14A-5-501.4 if an inspection can't happen because the owner or permit holder isn't ready
Processing time
After final inspections; allow several weeks
Renewal
None
Who files
Coordinated by the architect of record and the permit holder.

Good to know

Occupying a space that needs a certificate without one (or a partial/temporary certificate) is illegal. Many older Chicago storefronts have no certificate on file; a pure takeover with no construction doesn't create a new one, but any change of occupancy does.

Official source

DOB — Certificates of Occupancy · DOB — occupancy classification (Group A at 50+ occupants)

Get your personalized Chicago permit plan

Answer a few questions about your space and get every permit in order, with a timeline, a cost range, walkthroughs, and every application filled in for you to sign with Open.

Build my free plan

Last reviewed 2026-10-06. Guidance only, not legal advice.