Permit guides › Boston › BOS-TR-01

Long-Form Building Permit (Alteration / Change of Occupancy): Boston restaurant guide

Boston ISD (Building Division)

What it is

The building permit for major alterations or any change to a building's structure or use, such as turning retail into a restaurant. It also triggers zoning review, and a zoning refusal is how you get to the ZBA.

When a restaurant needs it

Change of use/occupancy, new construction, structural work, new signs, or a full restaurant build-out.

How to apply

Your licensed contractor files online in the ISD portal under 'Long Form/Alteration/Change of Occupancy' (or 'Erect/New Construction'), uploading stamped plans and all outside approvals at once.

Documents you’ll need

Fee
$50 base fee plus $10 per $1,000 of estimated work cost, paid upfront
Processing time
Several months to over a year, depending on zoning and plan review
Renewal
Work must start within 6 months of issuance (some projects can get a 180-day extension)
Who files
For a commercial space the applicant must be the licensed contractor doing the work (office staff may submit in the contractor's name).

Good to know

ISD doesn't collect outside approvals for you. Get Landmarks, Planning or Parks sign-offs yourself and upload them, or the permit won't be issued.

Official source

Boston — Long-Form Permit · Boston Permit Finder (status)

Get your personalized Boston permit plan

Answer a few questions about your space and get every permit in order, with a timeline, a cost range, walkthroughs, and every application filled in for you to sign with Open.

Build my free plan

Last reviewed 2026-10-06. Guidance only, not legal advice.