New Water/Wastewater Service — Tap Plan & Connection Fees: Austin restaurant guide

Austin Water — Utility Development Services

What it is

Approval of new or upsized water/wastewater connections and payment of tap and capital recovery fees.

When a restaurant needs it

New construction or a project that needs a new or larger meter/tap.

How to apply

A Texas-licensed Professional Engineer submits the tap plan through AB+C using the Commercial Tap Plan Checklist; pay connection fees once approved.

Documents you’ll need

Fee
Varies — see Austin Water UDS fee schedule (capital recovery and meter fees)
Processing time
Varies
Renewal
None
Who files
Tap plans must be prepared by a Texas-licensed Professional Engineer.

Good to know

No building permit will be issued until all tap fees are paid — get the tap plan in early.

Official source

Austin Water — new service connections

Get your personalized Austin permit plan

Answer a few questions about your space and get every permit in order, with a timeline, a cost range, walkthroughs, and every application filled in for you to sign with Open.

Build my free plan

Last reviewed 2026-10-06. Guidance only, not legal advice.