What it is
AFD reviews building and fire-system plans (sprinklers, fire alarm) under the 2024 IFC and performs the 'Fire Final for Certificate of Occupancy' inspection.
When a restaurant needs it
Every building permit or change of use; separate fire-system submittals when sprinklers or alarms are added or modified.
How to apply
Fire life-safety review happens inside DSD commercial plan review; fire system contractors upload sprinkler/alarm submittals through AFD's Fire System Plan Review Form, and inspections are requested through the AFD Inspection Request Intake Form.
Documents you’ll need
- Building plan set
- Sprinkler submittal (per AFD checklist)
- Fire alarm submittal with voltage-drop and battery calculations
Good to know
Fees must be paid before AFD schedules an inspection; inspection requests are taken Monday–Friday 8 a.m.–1 p.m.
Official source
AFD — Fire Plan Review · AFD — request a fire inspection
Answer a few questions about your space and get every permit in order, with a timeline, a cost range, walkthroughs, and every application filled in for you to sign with Open.